Workers have poured the first concrete for the nuclear island at Xuwei, in Jiangsu province. Most nuclear plants are built almost exclusively for the electricity grid. Xuwei is designed differently: it will work mainly as an industrial steam supplier, sending heat straight to nearby petrochemical refineries and surplus electricity to the regional network.

The trick is a two-step chain. The Hualong One, a third-generation pressurized water reactor, first turns demineralized water into saturated steam. The Chilong-1, a high-temperature gas-cooled reactor, takes that steam and heats it further, past saturation, into three separate grades of high-temperature steam tailored for refining. Plant operators will run both reactor types under one 'reactor-machine-heat' control architecture, which the reporting describes as a first for a commercial facility.

Chilong-1 was developed by China National Nuclear Corporation (CNNC) and Tsinghua University. It belongs to the fourth generation of reactor designs built around passive safety: it is meant to stay safe during severe failures, without operator action or external power. Its designers say the physics of the core prevents a meltdown even after complete coolant loss. Tsinghua researchers and project partners reported full-scale loss-of-coolant tests in 2023 and 2024, according to POWER magazine. NucNet describes Chilong One as a scaled-up version of the HTR-PM. Each module produces modest power on its own, so engineers can link several to match regional needs, and the high core temperatures make the reactor suited to large-scale hydrogen production, according to the reports.

The coverage does not agree on everything. One headline ties the January pour to the gas-cooled reactor, but World Nuclear News places it on the first Hualong One, unit 1. It reports that construction has now started on unit 3, which will house the Chilong One, rated at 660 MWe and designed to run for 60 years. The National Nuclear Safety Administration issued the construction licence for that unit on 2 November, valid until 2036. The safety results come from the designers and their project partners, and the reporting attributes those safety results to the designers and their project partners.

For the Lianyungang petrochemical industrial base, the plant is meant to become a permanent source of low-carbon heat and power. Once fully operational, the first phase is designed to deliver 32.5 million tonnes of industrial steam and over 11.5 billion kilowatt-hours of electricity each year. It would cut standard coal use by 7.26 million tonnes each year and prevent nearly 19.6 million tonnes of carbon dioxide emissions, according to official estimates. No commissioning date has been given.

The next milestone the plan names is full operation of the first phase. The first Hualong One has been under construction since 16 January, and unit 3 has now started.