Ford's first lower-cost EV batteries roll off a Michigan line

Ford has entered the battery business. The first lithium iron phosphate (LFP) cells are now rolling off the assembly line at the BlueOval Battery Park Michigan plant, and they are headed to Louisville, Kentucky, to power prototypes of the Fathom, an electric pickup Ford says will start under $30,000.
LFP is a lithium-ion battery built on iron phosphate instead of nickel and cobalt, and that choice helps keep costs down. LFP cells also typically hold up better after years of use and charging. The trade-off is energy: they store less energy per kilogram than nickel-based cells. CATL, the Chinese battery giant, claims 205 watt-hours per kilogram for its LFP cell as of 2024.
To get the chemistry running in Michigan, Ford turned to CATL, the leading global EV battery manufacturer. Ford uses CATL’s licensed technology and manufacturing expertise at the plant, and says it will be the first in the US to deliver LFP batteries for mainstream automotive use.
The route was not straight. A 2023 Ford filing had slated initial production at the Michigan plant for 2026, with 2,500 employees to start. Last December, Ford dissolved its battery joint venture with South Korea’s SK On, whose focus was nickel-based chemistries, while Ford pursued LFP and lithium-manganese. That filing gives the investment as $3.5 billion; another report puts it at $3 billion.
The cells are prismatic, meaning flat and rectangular, and they fit directly into the chassis. Ford chose that shape to cut structural costs. In its Universal Electric Vehicle (UEV) platform, the battery pack becomes the floor of the vehicle, so the battery does structural work instead of sitting as a separate box under the car. Ford claims this design needs 20% fewer parts, and says it designed the Fathom from the ground up for efficiency.
Speed is only half the job. The Michigan lines can deliver 40 cells every minute, which Ford says makes the plant one of the fastest LFP prismatic lines outside China. To keep up quality, Ford says employees use AI-powered image recognition to spot defects in real time. The company states its aim plainly: “Our goal is to make defective cells so rare that we track their frequency per billion cells rather than per million.” According to electrive, the prototype cells are being tested against CATL’s quality standards, and CATL employees have helped the production ramp-up in Marshall, Michigan.
The vehicle waiting for these cells is the Fathom, the first model on the UEV platform, named in August 2026. Ford’s own plan puts prototype builds with production-qualified parts at its Louisville Assembly Plant in the first quarter of 2027, with customer vehicles later that year. Ford says it spent eight months converting the Louisville plant from gas vehicles to a fully electric line. Preorders open in early 2027, at $28,350 for the standard-range model. CEO Jim Farley calls the Fathom a “breakthrough product” that is highly capable and still affordable.
Ford’s comparisons go further. It says the Fathom offers more interior space than a Toyota RAV4 and costs less to own over five years than a three-year-old used Tesla Model Y. The pickup will be the first vehicle to integrate Apple Maps directly into its navigation system, and it will be able to send power from its battery to a home or device. Ford has not disclosed battery specifications or range, which are the figures that will show how far LFP’s lower energy per kilogram can stretch. Farley said on the third-quarter earnings call that launch remains on track for Q4 2027, though Ford did not say whether launch means the start of production, of sales or of deliveries.
The program has also drawn political scrutiny in Washington. In a letter to Farley dated September 8, Transportation Secretary Sean Duffy said his department is “deeply alarmed” by Ford’s use of technology licensed from CATL, Bloomberg reported. Ford answers that its agreement with CATL is “a limited technology-licensing and services agreement, not a joint venture,” and that it owns the plant, controls the operation and employs the workforce. Twenty-six House Republicans on the Energy and Commerce Committee have also probed the partnership.
For buyers, the change is a pickup under $30,000 with a chemistry that typically holds up better over years of use. For Ford, the Michigan know-how will also support more affordable EVs and Ford Energy, its new battery energy storage business in Kentucky. The Michigan battery pack plant is due to be up and running in 2027, which Ford calls ahead of schedule. The next dates are prototype builds in the first quarter of 2027, preorders in early 2027, and a launch in the fourth quarter of 2027.