Ontario's Bruce Unit 5 starts core rebuild for 30 to 35 more years

On 1 November, technicians disconnected Unit 5 at the Bruce nuclear generating station in Ontario and began a comprehensive core rebuild. The job is a Major Component Replacement outage, a full overhaul of the reactor's core components that the operator expects to add 30 to 35 years to the unit's operating life.
The work marks the official midpoint of a privately financed, multi-billion-dollar Life-Extension Program that aims to modernize Units 3 through 8 by 2033. Inside the reactor vault, crews must replace 480 calandria tubes and an equal number of pressurized fuel channels, fit 960 feeder tubes, and hoist new steam generators into place. The stakes are a province whose electricity needs are set to climb fast, with officials projecting demand to rise 90 percent by 2050, driven by industrial expansion and electrification.
The crews are not starting cold. On Unit 4, engineers installed all 480 calandria tubes nearly a month ahead of schedule, a site record that beat the previous refit by 25 days; the fuel channels are now going in. Unit 3 went further. It returned to commercial service in June, more than seven months ahead of schedule, after teams used specialized robotics on the reactor face for the first time. That early restart came during peak summer demand and returned roughly $150 million to Ontario ratepayers through the Independent Electricity System Operator. Unit 6, the first reactor upgraded under the program, finished ahead of schedule and under budget in 2023, returning $52 million to consumers.
For Ontario households and businesses, the gain is a steady supply of low-carbon baseload electricity. Stephen Lecce, Ontario's Minister of Energy and Mines, said that extending the life of this critical asset “will deliver reliable, affordable electricity” and that 95 percent of Bruce Power's spending stays within Canada. The same reactors also supply medical isotopes used in cancer treatment, a service that continues for the international healthcare sector once the units are back online.
Bruce Power will now run overlapping outages continuously for the next seven years. Unit 7 shuts down for its upgrade in 2028, and Unit 8 follows in 2030. Provincial planners are also evaluating a second major overhaul for Units 1 and 2, which returned to service in 2012. Eric Chassard, Bruce Power's president and chief executive officer, said performance has improved with every refit as methods become more refined. The announcement gives no return date for Unit 5.