The last of 65 turbines went up in September, and by October the Revolution Wind farm was sending power at full capacity: 704 megawatts off the coast of Connecticut and Rhode Island. Ørsted, the Danish energy company developing the project, announced the milestone on Thursday, in an emailed statement after its quarterly earnings call. Revolution Wind is the third US utility-scale offshore wind farm to reach full commercial operation, after South Fork Wind near New York and Vineyard Wind near Massachusetts.
The farm started delivering smaller amounts of power in the spring, months before its turbines were all in place. Ørsted says it will provide enough electricity to power the equivalent of more than 350,000 New England homes. The carbon-free power is sold to three regional utilities: Rhode Island Energy, Eversource Energy and United Illuminating. The project carries a cost of $6.2 billion.
The farm was built against a hostile backdrop. Since President Donald Trump took office in January 2025, the US offshore wind sector has faced a series of political attacks. Before his second administration began, BloombergNEF projected that the US would build 39 gigawatts of offshore wind by 2035. It now expects 5.9 GW, a figure that reflects the handful of projects already completed or under construction at the start of last year.
Revolution Wind was halted twice in 2025. In August, the Interior Department issued a stop-work order citing unspecified national security threats, and a federal judge threw it out a month later. In late December, the administration issued new stop-work orders for all five offshore wind projects then under construction. Judges struck them down one by one, but developers had already lost huge sums and nearly missed key deadlines. In October, the Interior Department asked a federal court to reevaluate its 2023 approval of the farm's construction and operations plan. That move did not immediately affect the project's activities, but experts say it adds uncertainty around an installation that is now fully operational.
For the Northeast, the effect is practical. The farm adds a substantial new source of generation to a grid under pressure, and Revolution Wind and the country's other completed projects have already helped reduce grid stress during extreme weather events this year. Experts expect the carbon-free energy to help keep household utility bills in check across the region. Hillary Bright, executive director of the advocacy group Turn Forward, calls it “an essential boost of utility-scale electricity” for the power-hungry Northeast.
Orsted's next project is Sunrise Wind. The developer says it has finished installing all the wind-turbine foundations for the 924 MW farm off Long Island, New York, which is expected to be fully operational in the second half of next year.