The last of 65 turbines went up in September, and by October the Revolution Wind farm was sending power at full capacity: 704 megawatts off the coast of Connecticut and Rhode Island. Ørsted, the Danish energy company developing the project, announced the milestone on Thursday, in an emailed statement after its quarterly earnings call. Revolution Wind is the third US utility-scale offshore wind farm to reach full commercial operation, after South Fork Wind near New York and Vineyard Wind near Massachusetts.
El último de los 65 aerogeneradores se instaló en septiembre y, en octubre, el parque Revolution Wind ya enviaba electricidad a plena capacidad: 704 megavatios frente a las costas de Connecticut y Rhode Island. Ørsted, la compañía energética danesa que desarrolla el proyecto, anunció el hito el jueves, en un comunicado enviado por correo electrónico tras la presentación de sus resultados trimestrales. Revolution Wind es el tercer parque eólico marino de EE. UU. a escala comercial en alcanzar la explotación comercial plena, tras South Fork Wind, cerca de Nueva York, y Vineyard Wind, cerca de Massachusetts.
The farm started delivering smaller amounts of power in the spring, months before its turbines were all in place. Ørsted says it will provide enough electricity to power the equivalent of more than 350,000 New England homes. The carbon-free power is sold to three regional utilities: Rhode Island Energy, Eversource Energy and United Illuminating. The project carries a cost of $6.2 billion.
La instalación empezó a entregar pequeñas cantidades de energía en primavera, meses antes de que estuvieran colocados todos los aerogeneradores. Ørsted afirma que producirá electricidad suficiente para abastecer a el equivalente a más de 350.000 hogares de Nueva Inglaterra. La energía libre de carbono se vende a tres compañías eléctricas regionales: Rhode Island Energy, Eversource Energy y United Illuminating. El proyecto tiene un coste de 6.200 millones de dólares.
The farm was built against a hostile backdrop. Since President Donald Trump took office in January 2025, the US offshore wind sector has faced a series of political attacks. Before his second administration began, BloombergNEF projected that the US would build 39 gigawatts of offshore wind by 2035. It now expects 5.9 GW, a figure that reflects the handful of projects already completed or under construction at the start of last year.
El parque se construyó en un contexto hostil. Desde que el presidente Donald Trump asumió el cargo, en enero de 2025, el sector eólico marino de EE. UU. ha sufrido una serie de ataques políticos. Antes del inicio de su segunda Administración, BloombergNEF proyectaba que el país construiría 39 gigavatios de eólica marina para 2035. Ahora prevé 5,9 GW, una cifra que refleja el puñado de proyectos ya completados o en construcción a comienzos del año pasado.
Revolution Wind was halted twice in 2025. In August, the Interior Department issued a stop-work order citing unspecified national security threats, and a federal judge threw it out a month later. In late December, the administration issued new stop-work orders for all five offshore wind projects then under construction. Judges struck them down one by one, but developers had already lost huge sums and nearly missed key deadlines. In October, the Interior Department asked a federal court to reevaluate its 2023 approval of the farm's construction and operations plan. That move did not immediately affect the project's activities, but experts say it adds uncertainty around an installation that is now fully operational.
Revolution Wind fue detenido dos veces en 2025. En agosto, el Departamento del Interior emitió una orden de paralización alegando amenazas indeterminadas para la seguridad nacional, y un juez federal la anuló un mes después. A finales de diciembre, la Administración emitió nuevas órdenes de paralización para los cinco proyectos eólicos marinos que estaban entonces en construcción. Los jueces las anularon una a una, pero los promotores ya habían perdido enormes sumas y estuvieron a punto de incumplir plazos clave. En octubre, el Departamento del Interior pidió a un tribunal federal que reevaluara la aprobación de 2023 del plan de construcción y operación del parque. Esa medida no afectó de inmediato a las actividades del proyecto, pero los expertos señalan que añade incertidumbre en torno a una instalación que ahora funciona a plena capacidad.
For the Northeast, the effect is practical. The farm adds a substantial new source of generation to a grid under pressure, and Revolution Wind and the country's other completed projects have already helped reduce grid stress during extreme weather events this year. Experts expect the carbon-free energy to help keep household utility bills in check across the region. Hillary Bright, executive director of the advocacy group Turn Forward, calls it “an essential boost of utility-scale electricity” for the power-hungry Northeast.
Para el noreste, el efecto es práctico. El parque añade una nueva y sustancial fuente de generación a una red bajo presión, y Revolution Wind y los demás proyectos completados en el país ya han contribuido a aliviar la tensión en la red durante fenómenos meteorológicos extremos este año. Los expertos prevén que la energía libre de carbono ayude a contener las facturas de electricidad de los hogares en toda la región. Hillary Bright, directora ejecutiva del grupo de defensa Turn Forward, la describe como «un impulso esencial de electricidad a gran escala» para el Noreste, muy demandante de energía.
Orsted's next project is Sunrise Wind. The developer says it has finished installing all the wind-turbine foundations for the 924 MW farm off Long Island, New York, which is expected to be fully operational in the second half of next year.
El siguiente proyecto de Orsted es Sunrise Wind. La promotora afirma que ha terminado de instalar todas las cimentaciones de los aerogeneradores del parque de 924 MW frente a Long Island, en Nueva York, que se espera que esté plenamente operativo en la segunda mitad del próximo año.