News of progress
PrototypeSingle source

Boom Supersonic unveils prototype turbine core for jets and power

Languages for this article
Original · ENDEESFRITPT

Originally written in English. 6 languages available; yours is one click away.

Illustrative photo: Supersonic dive maneuver
Illustrative photo: NASA/Carla Thomas · Public domain · Wikimedia Commons

A 14,000-pound turbine core left Boom Supersonic's research and development facility on a truck bound for a dedicated test site at the Colorado Air and Space Port. It is the first complete core the company has unveiled, and it is built to do two jobs: power a jet engine that flies faster than sound, and generate electricity on the ground. Boom, best known for its Overture supersonic passenger airliner, plans to run it there by Thanksgiving.

The prototype, called Sprint Core, is the foundation for the Symphony jet engine and the Superpower 42-megawatt gas turbine. Inside, a six-stage high-pressure compressor feeds a combustion system with 24 fuel nozzles, then a single-stage high-pressure turbine. The compressor uses blisks, parts in which the blades and the central disk are made as a single piece from high-grade stainless steel and nickel-based alloys. The turbine blades are hollow and built from superalloys, metals designed to keep their strength at high temperature. Boom has fitted the core with nearly 1,000 sensors, about 2,000 once the supporting systems are counted, and some of them record data millions of times per second. The company is clear that this is an experimental prototype meant to gather engineering data, not an engine ready for production.

The move applies to electricity a technology first developed for supersonic flight, in a market where demand for additional power capacity is rising. To build the parts at scale, Boom has opened a $150 million manufacturing facility in Centennial, Colorado, spanning nearly 200,000 square feet across two buildings. Its Superpower Superfactory is already producing components while construction continues. Once fully operational, it should make parts representing about 85% of each turbine's mass, with more than 75 large manufacturing and inspection machines and up to 500 workers. The target is 1 GW of annual production, or 25 turbines, by 2028, rising to 2 GW, or 50 turbines, by 2029. First customer deliveries are planned for mid-2027.

What this changes depends on one thing the company has not yet shown: that the shared turbine design runs reliably. For a power buyer, a gas turbine that can be built in volume from a factory already producing parts would be a new supplier, but no customer is named in the announcement, and the first deliveries are still about a year and a half away at the planned timetable. Boom also announced an all-digital foundry for single-crystal turbine blades and vanes, which would remove the need for conventional tooling and could let engineers test new blade designs much faster. That foundry is still under development, with the first single-crystal components expected in 2027.

The expansion comes after the reported cancellation of a $1.25 billion agreement with data-center developer Crusoe covering 29 turbines. Boom is now looking for customers for its gas turbines. Its immediate task, as the company frames it, is to show that the core performs reliably before it scales production for both electricity generation and supersonic aviation.

1 GWAnnual production target by 2028 (25 turbines), rising to 2 GW by 2029