China's neutron source reaches 200 kW, twice its design power

Languages for this article
Original · ENDEESFRITPT

Originally written in English. 6 languages available; yours is one click away.

Photo: ChinaSpallationNeutronSource
Photo: Raysonho @ Open Grid Scheduler / Scalable Grid Engine · CC0 · Wikimedia Commons

On October 20, after nearly a month of beam commissioning, the China Spallation Neutron Source in Dongguan pushed its beam past 200 kW and began user operation at that level. The Institute of High Energy Physics of the Chinese Academy of Sciences (IHEP) announced the milestone on October 24. The figure is twice the beam power the facility was originally designed for in its first phase.

Raising power is where such machines usually stall. Changes in equipment parameters combine with effects such as space charge and beam impedance instability, and the beam starts losing particles. The accelerator team tuned key sections of the upgraded linear accelerator and made major changes to its operating mode. IHEP says this resolved the collective beam instability and pushed the beam density index above the highest level reported for comparable accelerators worldwide, while beam loss fell as power rose.

The upgrade is also moving on the hardware side. Over the summer shutdown, the team installed and tested the front-end equipment of the linear accelerator, all solid-state modulators and a third magnetic alloy cavity in the rapid cycling synchrotron. All CSNS-II accelerator equipment except the superconducting section is now in place. On the target side, a new target, T8, was installed and tested on September 25, with a cooling design built for 200 kW and new temperature monitoring that will inform the high-power target of CSNS-II. The facility's 11 neutron instruments open to users were also serviced.

For researchers in materials, life sciences and energy, the change comes once the upgrade is finished: a more capable neutron source. The 500 kW target is not yet reached, and IHEP has not announced a date for it. The next step is raising the linac beam energy to 300 MeV. CSNS-II is about halfway through construction, and a 1 kW-class 2 K helium refrigerator was installed on October 15.

200 kWBeam power in user operation, twice the phase-one design, per IHEP