Rising from the ridgelines of southern Laos, 133 wind turbines stand taller than the trees around them. Toukta Phonsala, 23, watches them from her wooden stilt house in Dak Wai village, her baby bouncing on her lap: “They’re bigger than trees.” Since August 2025, the 600-megawatt Monsoon Wind Power Project has been turning above her village, and its electricity flows across the border to Vietnam.

Hydroelectric dams have multiplied across Southeast Asia, but their output drops in the dry season, and critics lament their ecological impacts. Laos already hosts 90 hydropower plants, and dozens more stand in neighboring countries, so few optimal sites remain. Wind is now set to take off. The Monsoon project, built by a Chinese state firm and owned by a Thai-led consortium, covers an area the size of Singapore and cost $700 million. It is the first cross-border wind project in Asia and, according to AFP, the largest wind farm in Southeast Asia.

For the people who live beside it, the project has brought roads, improved access to fresh water and better health care. It has not brought reliable power. Residents still lose electricity during heavy storms, because Laos’ own grid is outdated and its state utility is heavily in debt. Toukta is glad that the country can send power abroad: “It’s better for development and can bring prosperity.”

For Vietnam, the gain is concrete. Vietnam, Southeast Asia’s fastest-growing economy, already imported hydropower from Laos, and the government warned in September of possible electricity shortages from next year because of delays in planned power projects. Thomas Jakobsen of Indochina Energy Partners estimates that the state utility EVN pays Monsoon around 6 cents per kilowatt-hour, 2 to 4 cents less than the Vietnamese rate. Monsoon, EVN and the Asian Development Bank declined to confirm that figure. EVN’s Ninh Xuan Hiep says the project is key to Vietnam’s net-zero target for 2050, and that by 2030 Laos imports could equal nearly 10% of Vietnam’s total installed capacity.

What opens next is a wider wind build-out. Monsoon plans to add 1,000 megawatts, and a Laos official counts 10 to 15 wind farm projects under development nationwide. The government is set to collect $180 million over the 25-year contract, including taxes and funds for community development and environmental protection. The operator’s general manager, Narut Boakajorn, says Laos has wind, hydro and solar resources in the same place, a combination he calls “something unique.”

600 megawattsIn operation since August 2025, the largest wind farm in Southeast Asia, according to AFP