The last of 65 turbines went up in September, and by October the Revolution Wind farm was sending power at full capacity: 704 megawatts off the coast of Connecticut and Rhode Island. Ørsted, the Danish energy company developing the project, announced the milestone on Thursday, in an emailed statement after its quarterly earnings call. Revolution Wind is the third US utility-scale offshore wind farm to reach full commercial operation, after South Fork Wind near New York and Vineyard Wind near Massachusetts.
A última das 65 turbinas foi instalada em setembro e, em outubro, o parque eólico Revolution Wind começou a fornecer energia à capacidade total: 704 megawatts ao largo da costa de Connecticut e Rhode Island. A Ørsted, empresa energética dinamarquesa que desenvolve o projeto, anunciou o marco na quinta-feira, num comunicado enviado por correio eletrónico após a apresentação dos resultados trimestrais. O Revolution Wind é o terceiro parque eólico offshore de grande escala dos EUA a atingir a plena exploração comercial, depois do South Fork Wind, perto de Nova Iorque, e do Vineyard Wind, perto de Massachusetts.
The farm started delivering smaller amounts of power in the spring, months before its turbines were all in place. Ørsted says it will provide enough electricity to power the equivalent of more than 350,000 New England homes. The carbon-free power is sold to three regional utilities: Rhode Island Energy, Eversource Energy and United Illuminating. The project carries a cost of $6.2 billion.
O parque começou a fornecer pequenas quantidades de energia na primavera, meses antes de todas as turbinas estarem instaladas. A Ørsted afirma que o parque fornecerá eletricidade equivalente à necessária para abastecer mais de 350 000 lares da Nova Inglaterra. A energia sem emissões de carbono é vendida a três concessionárias regionais: Rhode Island Energy, Eversource Energy e United Illuminating. O projeto tem um custo de 6,2 mil milhões de dólares.
The farm was built against a hostile backdrop. Since President Donald Trump took office in January 2025, the US offshore wind sector has faced a series of political attacks. Before his second administration began, BloombergNEF projected that the US would build 39 gigawatts of offshore wind by 2035. It now expects 5.9 GW, a figure that reflects the handful of projects already completed or under construction at the start of last year.
O parque foi construído num contexto hostil. Desde que o Presidente Donald Trump tomou posse, em janeiro de 2025, o setor eólico offshore dos EUA tem enfrentado uma série de ataques políticos. Antes do início do seu segundo mandato, a BloombergNEF previa que os EUA construíssem 39 gigawatts de energia eólica offshore até 2035. Agora, prevê 5,9 GW, um valor que reflete o pequeno número de projetos já concluídos ou em construção no início do ano passado.
Revolution Wind was halted twice in 2025. In August, the Interior Department issued a stop-work order citing unspecified national security threats, and a federal judge threw it out a month later. In late December, the administration issued new stop-work orders for all five offshore wind projects then under construction. Judges struck them down one by one, but developers had already lost huge sums and nearly missed key deadlines. In October, the Interior Department asked a federal court to reevaluate its 2023 approval of the farm's construction and operations plan. That move did not immediately affect the project's activities, but experts say it adds uncertainty around an installation that is now fully operational.
O Revolution Wind foi travado duas vezes em 2025. Em agosto, o Departamento do Interior emitiu uma ordem de suspensão de trabalhos invocando ameaças à segurança nacional não especificadas, e um juiz federal anulou-a um mês depois. No final de dezembro, a administração emitiu novas ordens de suspensão para os cinco projetos eólicos offshore então em construção. Os tribunais anularam-nas uma a uma, mas os promotores já tinham perdido somas avultadas e quase falharam prazos essenciais. Em outubro, o Departamento do Interior pediu a um tribunal federal que reavaliasse a aprovação de 2023 do plano de construção e exploração do parque. Essa iniciativa não afetou de imediato as atividades do projeto, mas os especialistas afirmam que introduz incerteza em torno de uma instalação que está agora totalmente operacional.
For the Northeast, the effect is practical. The farm adds a substantial new source of generation to a grid under pressure, and Revolution Wind and the country's other completed projects have already helped reduce grid stress during extreme weather events this year. Experts expect the carbon-free energy to help keep household utility bills in check across the region. Hillary Bright, executive director of the advocacy group Turn Forward, calls it “an essential boost of utility-scale electricity” for the power-hungry Northeast.
Para o Nordeste, o efeito é concreto. O parque acrescenta uma nova fonte substancial de produção a uma rede elétrica sob pressão, e o Revolution Wind, juntamente com os restantes projetos concluídos no país, já contribuiu este ano para aliviar a tensão na rede durante eventos meteorológicos extremos. Os especialistas esperam que a energia sem emissões de carbono ajude a conter as faturas de eletricidade das famílias na região. Hillary Bright, diretora executiva do grupo de defesa Turn Forward, classifica-a como «um impulso essencial de eletricidade de grande escala» para o Nordeste, uma região muito dependente de energia.
Orsted's next project is Sunrise Wind. The developer says it has finished installing all the wind-turbine foundations for the 924 MW farm off Long Island, New York, which is expected to be fully operational in the second half of next year.
O próximo projeto da Ørsted é o Sunrise Wind. A promotora afirma ter concluído a instalação de todas as fundações das turbinas do parque de 924 MW ao largo de Long Island, Nova Iorque, que deverá estar totalmente operacional no segundo semestre do próximo ano.