34-MW Hydrogen Turbine Starts Test Run in Lingen

A gas turbine capable of generating electricity from hydrogen has recently been installed next to the Emsland gas power plant in Lingen. RWE commissioned it on November 6, 2026, and has started test operation. The turbine was built by the Japanese group Kawasaki Heavy Industries (KHI). At 34 megawatts, it is the largest turbine of its kind in Europe, according to RWE. It can run on hydrogen, natural gas or any mixture of the two.
The fuel comes from the Get H2 Nukleus electrolyzer on the neighboring site. Electrolyzers use electricity to split water into hydrogen and oxygen. Wind and solar plants are typically shut down today when they cannot feed their power into the grid. If that electricity is instead used to produce hydrogen, the hydrogen can be stored and, when needed, such as during calm periods or at night, converted back into electricity in gas turbines. RWE already operates a 14-megawatt electrolyzer and is building a 300-megawatt one at the site.
The schedule has slipped. RWE had originally promised commissioning for mid-2024; the turbine is now starting just over two years later. Nikolaus Valerius, head of RWE Generation, puts the leap this way: “The new plant will deliver up to ten times as much output as previous hydrogen turbines.” The operating experience is an important foundation for deploying even larger plants. The performance figures come from RWE and KHI themselves.
This is a field trial. RWE and KHI plan to test operation with up to 100% hydrogen on an industrial scale over the coming months. The test program covers different operating modes and load conditions of the kind flexible power plants can encounter. Only the results of these tests will show whether the turbine behaves on pure hydrogen in everyday use as the companies expect.
For the power grid, storage is what matters most. Valerius sees the technology as an important milestone that could eventually supply “hundreds of thousands of households reliably” with electricity. The road ahead is longer: new RWE gas plants will remain on natural gas for now. The three new gas plants for which RWE received awards in the tender for new power plants are also meant to run on hydrogen later.
Next up are the tests with up to 100% hydrogen, in the coming months. At the same site, RWE is building a 300-megawatt electrolyzer.