Heat pump turns paper mill waste heat into 120°C steam

In a paper mill in Weißenborn, in the German state of Hesse, heat produced by paper making is now turned into steam instead of being lost. A 1.2-megawatt (MW) heat pump, built by a research team involving the Fraunhofer Institution for Energy Infrastructures and Geotechnologies (IEG), was tested at a plant run by Felix Schoeller GmbH & Co. KG.
Industrial processes run on steam well above atmospheric pressure, at temperatures above 100°C. Making that steam usually means burning fossil fuels, especially natural gas, which releases CO2 and other greenhouse gases. The team's answer is a two-stage heat pump, a machine that uses electricity to move heat from a cooler place to a hotter one. It captures heat from paper production at 30 to 70°C and lifts it to about 120°C, which is enough to make usable industrial steam.
During its first about 300 operating hours in 2026, the pump produced an average steam output of around 700 kW, roughly 1.2 tons of steam per hour at about 2.3 bar. Its performance factor of 2.30 means it delivered more than twice as much useful heat as the electricity needed to run it. “Industrial companies need solutions that combine climate protection, energy supply security, and competitiveness,” said Reuven Paitazoglou, the project's manager. “High-temperature heat pumps make it possible to economically harness previously unused energy sources for production.”
For a mill, the gain is in gas. The institute estimates the pump could prevent up to 600 tons of CO2 a year if it runs 4,000 to 5,000 hours, or about 100 kilograms of CO2 per megawatt-hour of heat compared with steam made from natural gas. That figure depends on running hours far above the 300 measured so far. The project also sees possible uses in pharmaceutical and food plants, although the trial has only taken place at one paper mill.
Full-load tests started in September 2026. The team will now evaluate the system under real industrial conditions for one year, and expects further improvements before the EU-funded project ends in 2027. Fraunhofer IEG coordinated the scientific side of the tests and built the monitoring system that tracks performance, while the team examined how the pump fits into existing production processes and steam networks.